Contractor Delay Clause: The Per-Day Amount
When a rehab runs late, the owner pays interest, taxes and insurance on every extra day. A delay clause in the contract makes the contractor share that cost. The amount per day has to be defensible: a reasonable estimate of the loss, not a punishment.
The steps
- Work out your daily carrying cost.
- Set the per-day amount at or near it.
- Add exceptions for delays that are not the contractor’s fault.
- Compare the clause’s effect with the contract price (the contractor deposit).
A worked example
Example (illustrative arithmetic, not typical figures)
Your daily carry is $100. The contractor finishes 15 days late. Every figure is a made-up round number.
| Per-day amount in the contract | Recovered over 15 days | Recovered − your carry ($1,500) |
|---|---|---|
| $50 | $750 | −$750 (covers half) |
| $100 | $1,500 | $0 (matches your loss) |
| $150 | $2,250 | +$750 (above your loss, risks a penalty finding) |
A clause at your carrying cost makes you whole: $100 a day for 15 days is $1,500. A clause at $50 recovers half. A clause at $150 recovers more than you lost, which is the version most likely to be challenged as a penalty.
Make the clause fair and the contractor is likelier to sign it. Define the completion date, list the delays that do not count (weather, owner changes, late permits), and consider a matching bonus for finishing early. A contractor who is paid to be early and charged to be late has a reason to plan (paying a rush fee).
Making it routine
- Know your daily carrying cost.
- Write the completion date and the exceptions clearly.
- Set the per-day amount near your loss.
- Have a construction attorney review it.