Contractor Delay Clause: The Per-Day Amount

By DeskTech HQ · · 1 min read

When a rehab runs late, the owner pays interest, taxes and insurance on every extra day. A delay clause in the contract makes the contractor share that cost. The amount per day has to be defensible: a reasonable estimate of the loss, not a punishment.

The steps

  1. Work out your daily carrying cost.
  2. Set the per-day amount at or near it.
  3. Add exceptions for delays that are not the contractor’s fault.
  4. Compare the clause’s effect with the contract price (the contractor deposit).

A worked example

Example (illustrative arithmetic, not typical figures)

Your daily carry is $100. The contractor finishes 15 days late. Every figure is a made-up round number.

Per-day amount in the contract Recovered over 15 days Recovered − your carry ($1,500)
$50 $750 −$750 (covers half)
$100 $1,500 $0 (matches your loss)
$150 $2,250 +$750 (above your loss, risks a penalty finding)

A clause at your carrying cost makes you whole: $100 a day for 15 days is $1,500. A clause at $50 recovers half. A clause at $150 recovers more than you lost, which is the version most likely to be challenged as a penalty.

Make the clause fair and the contractor is likelier to sign it. Define the completion date, list the delays that do not count (weather, owner changes, late permits), and consider a matching bonus for finishing early. A contractor who is paid to be early and charged to be late has a reason to plan (paying a rush fee).

Making it routine

  1. Know your daily carrying cost.
  2. Write the completion date and the exceptions clearly.
  3. Set the per-day amount near your loss.
  4. Have a construction attorney review it.

Run your own numbers

Use the free holding cost calculator below to see your daily carrying cost on a project.

Quick answers

How do I size the per-day amount?

Use your daily carrying cost as the reasonable estimate of loss.

Can I charge more than my loss?

A clause far above actual loss can be unenforceable as a penalty.

What about delays that are not the contractor's fault?

Write exceptions for weather, change orders and permit delays.

Do contractors accept these clauses?

Some do, often with a matching bonus for early finish.

Do the numbers in this guide apply to my project?

No. The figures are made up for the example. They are not typical.

Keep reading

Flip project management

Mid-Project Cleanups vs One Final Clean

Learn how to compare paying for cleanups during a rehab with one big final clean, and the odds of finish damage that make the extra cleanups pay.

· 2 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.