Long-Lead Items: When to Order Before the Work Starts
The kitchen install is scheduled for week 5. The cabinets take eight weeks to arrive. If the order goes in after the demolition is finished in week 3, the crew finishes everything else and then waits.
The steps
- Mark the long-lead items on your schedule and the week each one is needed (critical path).
- Get each lead time, deposit and cancellation term in writing.
- For each ordering date, compute the arrival week and the weeks of delay.
- Price the delay at your weekly holding cost (holding costs).
- Add the expected cost of cancelling if the plan changes, and compare the options.
A worked example
Example (illustrative arithmetic, not supplier terms)
Cabinets cost $7,200 with an 8-week lead time and are needed in week 5. Holding cost is $300 a week. Cancelling an order costs a 25% restocking fee ($1,800). Assumed odds that the order has to be cancelled: 0% if ordered after demolition (scope is certain), 5% if ordered at the start, 25% if ordered before closing (the deal might fall through). Every figure is a made-up round number.
| Order placed | Arrives | Weeks of delay | Delay cost | Expected cancel cost | Total |
|---|---|---|---|---|---|
| Week 3, after demolition | Week 11 | 6 | $1,800 | $0 | $1,800 |
| Week 0, at the start | Week 8 | 3 | $900 | 5% × $1,800 = $90 | $990 |
| Week −2, before closing | Week 6 | 1 | $300 | 25% × $1,800 = $450 | $750 |
Waiting for certainty is the most expensive choice here: $1,800 against $750. Ordering before closing is the cheapest on paper, but the $450 is an expected cost, and the real outcome is either nothing or a $1,800 loss, and the deposit may be at risk too (buying materials early).
The middle option is a reasonable default: order at the start, once the scope is signed, and pick items you are confident about. If you can change only the installation week, a schedule buffer may absorb part of the delay (schedule buffer).
Making it routine
- List long-lead items on the scope of work with their lead times (scope of work).
- Order as soon as the scope for that item is final.
- Get deposits, cancellation terms and delivery dates in writing.
- Record actual lead times so your next schedule uses real numbers.
Run your own numbers
Use the free holding cost calculator below to price each week an item delays the job.