Buying Rehab Materials Early: Discount vs Carrying Cost
A supplier offers 6% off if you buy the flooring, cabinets and fixtures now. The job starts in three months. The discount is real. So is the cost of paying for materials three months before you need them.
The steps
- Total the materials you would buy now and the discount offered.
- Add the interest on that money for the months you would hold it (holding costs).
- Add storage and insurance for the same months.
- Subtract both from the discount to get the net saving.
- Stress it: what if some of the materials are not used?
A worked example
Example (illustrative arithmetic, not market data)
Materials $18,000, discount 6%, bought three months before use. Money costs 11% a year, and storage and insurance cost $150 a month. Every figure is a made-up round number.
| Item | Amount |
|---|---|
| Discount (6% of $18,000) | $1,080 |
| Interest (11% for 3 months) | −$495 |
| Storage and insurance (3 × $150) | −$450 |
| Net saving | $135 |
The carrying cost is $945, or 5.25% of the materials, so the 6% discount only just wins (cash timeline).
Now the stress. If the scope changes and 20% of the materials ($3,600) cannot be used, and the return costs a 15% restocking fee, the loss is $540. The net saving becomes $135 − $540 = −$405. Break-even is an unused share of $135 ÷ ($18,000 × 15%) = 5%. If more than 5% of the order may go unused, the early purchase loses money (cost overrun decisions).
So buy early only what is certain, and keep the rest for later, when the plan is final (contingency sizing).
Making it routine
- Ask suppliers for the discount, the return terms and a delivery date in writing.
- Run the carrying cost before you commit.
- Buy early only items already in the signed scope.
- Record the actual saving against the plan (profit variance).
Run your own numbers
Use the free holding cost calculator below to add the cost of carrying early purchases to your timeline.