Material Waste Factor: How Much Extra to Order

By DeskTech HQ · · 2 min read

A flooring crew runs out of boards on the last room. The supplier has more, but not from the same batch, and the order takes three days. The extra material you skipped would have cost a fraction of what the shortage does. The question is how much extra is enough.

The steps

  1. Measure the area and price the material per unit.
  2. Price the cost of each allowance: the extra units times the price.
  3. Price a shortage: a second order, shipping, and the days of delay times your holding cost per day (holding costs).
  4. Divide the extra cost of the larger allowance by the cost of a shortage. That is the chance of a shortage at which the larger allowance breaks even.
  5. Compare it with how likely the smaller allowance is to fall short for this job.

A worked example

Example (illustrative arithmetic, not quotes or standards)

1,000 square feet of flooring at $3 a square foot. A 5% allowance orders 1,050 square feet; a 10% allowance orders 1,100. A shortage costs $120 in shipping and three days of delay at $150 a day: $120 + $450 = $570. Every figure is a made-up round number.

The larger allowance costs 50 square feet more: 50 × $3 = $150.

Chance the 5% order falls short Expected shortage cost (× $570) Extra cost of the 10% order Value of ordering 10%
10% $57 $150 −$93
26.3% $150 $150 $0
40% $228 $150 +$78
Break-even $150 ÷ $570 = 26.3%

If the smaller order has less than about a one-in-four chance of falling short, the extra 5% is not worth buying. A simple rectangular room with an experienced installer may be safely under that. A pattern, diagonal layout or many small rooms raises the chance a lot. The answer depends on the job, not on a rule (long-lead items).

Leftover material is not wasted: a few spare boxes of the same batch make later repairs match, and you can leave some with the house. Price that benefit too. Keep the extra stored dry and labeled with the batch number (buying materials early).

Making it routine

  1. Ask the installer for the allowance they recommend for this layout.
  2. Order everything for a room from the same batch.
  3. Record material used against material ordered after each job.
  4. Use your own records to set the allowance next time.

Run your own numbers

Use the free holding cost calculator below to see what each day of delay costs on your project.

Quick answers

What is a waste factor?

The extra material you order beyond the measured amount, to cover cuts, mistakes, damage and pieces that do not fit.

How do I choose one?

Compare the cost of the extra material with the cost of running short, then ask how likely a shortage is at each allowance.

What does running short cost?

A second order, shipping, a possible mismatch in color or batch, and days of delay while holding costs keep running.

Is there a standard percentage?

This guide uses none. Layout, pattern and the installer's experience all change the right allowance. Ask your installer.

Do the numbers in this guide apply to my project?

No. The area, price and costs are made up for the example. They are not quotes or standards.

See DeskTech Deals →

Keep reading

Flip project management

Drying Time Before Flooring: Wait or Rush?

Learn how to weigh the holding cost of waiting for a subfloor to dry against the chance of flooring failure if you rush, and the odds that favor waiting.

· 2 min read
Flip project management

Rehab Contingency: Sizing the Buffer by Risk

Learn how to size a rehab contingency by the risk of each line item instead of one flat percentage, with a worked example and its effect on planned profit.

· 1 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.