When a Rehab Runs Over: Compare Your Options in Dollars

By DeskTech HQ · · 2 min read

Overruns happen on most rehabs. The question is not whether, but what to do when the surprise lands. Putting each choice in dollars keeps the decision from becoming an argument or a panic.

The three usual choices

  • Pay it. Accept the extra cost and keep the scope.
  • Cut scope. Drop or downgrade an item to offset the cost.
  • Renegotiate. Ask the contractor to share part of the overrun.

A worked example

Example (illustrative arithmetic, not market data)

Take the project from the profit and ROI guide, where the planned net profit is $30,720 and selling costs are 8%. After demolition, the contractor finds problems that add $8,000 to the rehab. The investor’s cash cushion is $7,120 (cash reserve). Every figure is a made-up round number.

Item A: Pay it B: Cut scope C: Renegotiate
What changes add $8,000 skip a $5,000 upgrade; value falls $4,000 contractor absorbs 10% of the overrun
Added cost $8,000 $8,000 − $5,000 = $3,000 90% × $8,000 = $7,200
Lost sale proceeds none $4,000 × 0.92 = $3,680 none
Profit left $30,720 − $8,000 = $22,720 $30,720 − $3,000 − $3,680 = $24,040 $30,720 − $7,200 = $23,520
Cash needed now $8,000 $3,000 $7,200
Against the $7,120 cushion $880 short covered $80 over

In this example cutting scope leaves the most profit, $24,040, which is $1,320 more than paying the full overrun and $520 more than renegotiating. It also needs the least cash. The comparison changes if the cut lowers the value by more, or if the contractor will absorb more.

What to do

  1. Get the cause of the overrun in writing, with a price.
  2. Put each option in dollars: added cost, lost proceeds, cash needed.
  3. Check the cash against the reserve.
  4. Write any change into a signed change order (contractor payments and change orders).
  5. Update the budget the same day (rehab estimates).
  6. Recheck the break-even price (break-even price).

Run your own numbers

Use the free holding cost calculator below to see what delay from an overrun adds to the cost.

Quick answers

What should an investor do when a rehab goes over budget?

Find out what caused it, then compare the choices in dollars: pay the overrun, cut scope, or renegotiate. Compare each by the profit left, the cash needed now and the effect on the finished value.

Is cutting scope always cheaper?

Not always. Dropping an item saves its cost, but if it also lowers the finished value or the speed of the sale, part of the saving is lost. The comparison needs both sides.

When does renegotiating work?

When the overrun comes from a change the contractor can price differently, or a mistake in the original bid. Work from the written scope and keep any agreement in writing.

Why compare cash needed, not only profit?

A choice that leaves the best profit still fails if the cash is not there when the bill is due. Comparing cash needed shows which choices are possible.

Do the numbers in this guide apply to my project?

No. The overrun, savings, value effect and negotiation result are made up for the example and are not market data. Use your own figures and your contractor's written scope.

Keep reading

Flip project management

Material Waste Factor: How Much Extra to Order

Learn how to choose a waste allowance for flooring, tile and trim by comparing the cost of extra material with the cost of running short.

· 2 min read
Flip project management

Rehab Contingency: Sizing the Buffer by Risk

Learn how to size a rehab contingency by the risk of each line item instead of one flat percentage, with a worked example and its effect on planned profit.

· 1 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.