Re-Inspection Fee for Contractors: The Failed Visits
A draw inspector arrives and the work is not ready. The visit is wasted and the next one costs again. A fee charged to the contractor for failed visits can change that. The question is how many failed visits per job the fee must prevent to cover its setup.
The steps
- Price one failed visit: the inspector’s fee plus your time.
- Price the program: time to write terms and track visits, per job.
- Break-even avoided visits per job = program cost ÷ cost per failed visit.
- Compare with how many failed visits your jobs have (draw inspector pay).
A worked example
Example (illustrative arithmetic, not benchmarks)
A failed visit costs $75 for the inspector and 20 minutes of time at $60 an hour ($20), so $95. The program costs $38 per job. Every figure is a made-up round number.
| Failed visits avoided per job | Cost avoided (visits × $95) | Avoided − $38 |
|---|---|---|
| 0.2 | $19 | −$19 |
| 0.4 | $38 | $0 (break-even) |
| 1 | $95 | +$57 |
| 2 | $190 | +$152 |
The program pays at 0.4 avoided failed visits per job: $38 ÷ $95. A contractor who calls for an inspection before the work is ready is the target, and a fee changes that habit.
The fee must be in the contract before work starts, and it should apply only to visits where the work was not ready, not to visits that find defects. Check the state’s rules on charging contractors (pre-inspection dry run).
Making it routine
- Put the fee in the contract before work starts.
- Apply it only when work was not ready.
- Log failed visits by contractor.
- Check state rules on fees and deductions.
Run your own numbers
Use the free fix-and-flip loan sizer below to see how a delayed inspection adds interest to a rehab loan.