Retainage 10% or 5%: The Punch-List Odds

By DeskTech HQ · · 2 min read

Retainage holds back part of each draw until the work is done. A larger share gives more to finish the punch list if the contractor walks. It also costs the contractor money to wait. The question is how likely a punch-list overrun has to be for 10% to beat 5%.

The steps

  1. Find the extra amount held: (10% − 5%) × the total draws.
  2. Price the extra cost: the contractor’s financing on that amount, passed into bids.
  3. Find the shortfall the extra holdback would cover in a bad finish.
  4. Break-even chance = extra cost ÷ shortfall covered (lien waivers on draws).

A worked example

Example (illustrative arithmetic, not benchmarks)

On $60,000 of draws, 10% holds $6,000 and 5% holds $3,000, so $3,000 more. Financing it at 1% a month for 2 months costs $60. A bad finish has a $4,000 punch list, so the extra holdback covers $1,000 that the 5% would miss. Every figure is a made-up round number.

Chance of a punch-list overrun Expected shortfall covered (chance × $1,000) Covered − $60
3% $30 −$30
6% $60 $0 (break-even)
10% $100 +$40
20% $200 +$140

The larger holdback pays at a 6% chance of a punch-list overrun: $60 ÷ $1,000. For a first-time contractor, that chance is likely higher. For a contractor with a long record, it may be lower.

The extra cost to contractors shows up in their bids. A tiered rule works: 10% for new contractors and 5% for proven ones. Check the state’s retainage rules and release timing first.

Making it routine

  1. Set the holdback in the loan documents and the contract.
  2. Use a higher share for new contractors.
  3. Release at final inspection and a lien waiver.
  4. Check the state’s rules and caps.

Run your own numbers

Use the free fix-and-flip loan sizer below to see how holdbacks change the amount funded at each draw.

Quick answers

What is retainage?

A share of each draw held back until the work is finished.

What does a larger holdback cost?

Contractors may price their financing into bids.

What does it buy?

Money in hand to finish the punch list if the contractor leaves.

What is the break-even chance?

The added cost divided by the shortfall the larger holdback covers.

Do the numbers in this guide apply to my draws?

No. The amounts and odds are made up for the example. They are not benchmarks.

Keep reading

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.