Saturday Material Delivery: The Crew-Day Odds That Pay
A crew waiting on materials is paid to wait. If the delivery that was due Friday slips to Monday, the crew may lose a day. A Saturday delivery costs extra. The question is how likely the slip has to be to justify the fee.
The steps
- Take the Saturday delivery fee.
- Cost a lost crew day: idle wages plus a day of carrying cost.
- Break-even chance = fee ÷ cost of a lost day.
- Compare with how reliable the supplier’s weekday deliveries are (paying a rush fee to finish faster).
A worked example
Example (illustrative arithmetic, not quotes or predictions)
Saturday delivery costs $75. A lost crew day costs $480. Every figure is a made-up round number.
| Chance the weekday delivery slips | Expected cost avoided (chance × $480) | Avoided − $75 |
|---|---|---|
| 5% | $24 | −$51 |
| 15.6% | $75 | $0 (break-even) |
| 30% | $144 | +$69 |
| 50% | $240 | +$165 |
Paying for Saturday delivery makes sense if the weekday delivery slips more than about one time in six: $75 ÷ $480. A supplier with a poor record clears that easily. A reliable one does not.
The better fix is usually earlier ordering. Long-lead items should be ordered before the crew needs them, not on the day before (long-lead items).
Making it routine
- Track delivery slips by supplier.
- Order critical items a week ahead.
- Compute the break-even chance.
- Pay for Saturday only on critical items.