Saturday Material Delivery: The Crew-Day Odds That Pay

By DeskTech HQ · · 1 min read

A crew waiting on materials is paid to wait. If the delivery that was due Friday slips to Monday, the crew may lose a day. A Saturday delivery costs extra. The question is how likely the slip has to be to justify the fee.

The steps

  1. Take the Saturday delivery fee.
  2. Cost a lost crew day: idle wages plus a day of carrying cost.
  3. Break-even chance = fee ÷ cost of a lost day.
  4. Compare with how reliable the supplier’s weekday deliveries are (paying a rush fee to finish faster).

A worked example

Example (illustrative arithmetic, not quotes or predictions)

Saturday delivery costs $75. A lost crew day costs $480. Every figure is a made-up round number.

Chance the weekday delivery slips Expected cost avoided (chance × $480) Avoided − $75
5% $24 −$51
15.6% $75 $0 (break-even)
30% $144 +$69
50% $240 +$165

Paying for Saturday delivery makes sense if the weekday delivery slips more than about one time in six: $75 ÷ $480. A supplier with a poor record clears that easily. A reliable one does not.

The better fix is usually earlier ordering. Long-lead items should be ordered before the crew needs them, not on the day before (long-lead items).

Making it routine

  1. Track delivery slips by supplier.
  2. Order critical items a week ahead.
  3. Compute the break-even chance.
  4. Pay for Saturday only on critical items.

Run your own numbers

Use the free holding cost calculator below to see what a lost day costs on your project.

Quick answers

What is the break-even chance?

The delivery fee divided by what a lost crew day costs.

What does a lost crew day cost?

Wages for idle workers, plus the day of carrying cost.

Can I just order earlier?

Often, yes. That is the cheaper fix when it works.

Are there delivery limits?

Local noise and work-hour rules may limit weekend deliveries.

Do the numbers in this guide apply to my project?

No. The fee, cost and odds are made up for the example. They are not quotes or predictions.

Keep reading

Flip project management

Ask for a Photo of Each Delivered Material Pallet

Learn how to price asking the contractor for a photo of each delivered material pallet and find the short-shipment chance at which two minutes pays.

· 1 min read
Flip project management

Contractor Delay Clause: The Per-Day Amount

Learn how to size a per-day amount for a contractor delay clause so it covers your daily carrying cost, and why it must be a reasonable estimate.

· 1 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.