Check Photo Dates on Draw Requests: The Odds
A draw request shows photos of work done. If the photos are from last month, or from another job, the draw may be for work not done. A glance at the date stored in each file takes three minutes. The question is how likely reused photos are for the check to pay.
The steps
- Price the check: minutes × the value of your time.
- Estimate the cost of paying for work not done: the draw at risk.
- Break-even chance = cost ÷ draw at risk.
- Pair it with the inspection (draw inspections: cost vs overpayment saved).
A worked example
Example (illustrative arithmetic, not predictions)
The check takes 3 minutes at $60 an hour: $3. Paying for work not done would cost $3,000. Every figure is a made-up round number.
| Chance photos are reused | Expected cost avoided (chance × $3,000) | Avoided − $3 |
|---|---|---|
| 0.05% | $1.50 | −$1.50 |
| 0.1% | $3.00 | $0 (break-even) |
| 0.5% | $15.00 | +$12.00 |
| 1% | $30.00 | +$27.00 |
The check pays at a 0.1% chance of reused photos: $3 ÷ $3,000. It is a quick screen with a high payoff if it ever catches one.
Open the file details on a phone or computer and look at the date taken. A missing date or one that does not match the work period is a reason to ask for new photos, not a finding of fraud. Photo dates can be edited, so keep the inspection as the real check (how many draw photos).
Making it routine
- Check the date taken on the photos.
- Ask for new photos if a date does not fit.
- Do not accuse; ask.
- Rely on the inspection for the real check.
Run your own numbers
Use the free fix-and-flip loan sizer below to see how an overpaid draw changes the funds left for a rehab.