What Is Your Time Worth on a Flip? Profit Per Hour
A flip that “made $29,200” took 220 hours of your life. That is $132.73 an hour, or, if the deal makes only $2,080, $9.45 an hour. The same project is a good job or a bad one depending on the hours. Most investors never count them.
The steps
- Track your hours by task for the whole project.
- Profit per hour = profit ÷ total hours.
- Cost per hour of help = what you would pay ÷ hours it saves.
- Compare the two, and ask what you would do with the saved hours.
A worked example
Example (illustrative arithmetic, not a benchmark)
Every figure is a made-up round number. Profit as planned is $29,200, and as it actually came out is $2,080 (profit variance).
| Task | Hours |
|---|---|
| Finding and analyzing the deal | 55 |
| Project management | 90 |
| Selling | 25 |
| Bookkeeping and admin | 20 |
| Travel and site visits | 30 |
| Total | 220 |
| Result | Calculation | Profit per hour |
|---|---|---|
| As planned | $29,200 ÷ 220 | $132.73 |
| As it came out | $2,080 ÷ 220 | $9.45 |
Would a project manager pay? Suppose hiring one costs $3,000 and saves 60 hours of project management and travel.
| Item | Do it yourself | With a project manager |
|---|---|---|
| Profit | $29,200 | $26,200 |
| Your hours | 220 | 160 |
| Profit per hour | $132.73 | $163.75 |
| Cost of help per hour saved | $3,000 ÷ 60 = $50.00 |
Paying $50 an hour for work you would do at $132.73 an hour leaves you with more per hour, and 60 hours free to find another deal. But total profit is $3,000 lower on this deal. Whether the trade is worth it depends on what the freed hours would earn (deal sourcing funnel).
Using the number
- Log hours weekly on every project (weekly scorecard).
- Compare profit per hour across your projects (year-end review).
- Test help on the stage that eats the most hours, and check the cost against the schedule (contractor payment schedule).
- Look at cash, return and downside as well (choosing between deals).
Run your own numbers
Use the free holding cost calculator below to see the carrying cost of the extra weeks your own hours may add.