The Final Draw: What to Hold Back Until the Work Is Done
The last draw is the easiest to approve. The house looks done, the photos are clean, and the borrower is already talking about a buyer. It is also the draw where a gap between “looks done” and “is done” is most expensive.
The steps
- Write the retainage percentage and the final-release conditions into the loan and draw documents (draw schedule).
- At the final request, inspect and list every unfinished item with an estimated cost (site visit report).
- Collect final lien waivers from everyone who worked on the property.
- Compute the exposure if the borrower stopped now: unfinished work plus unpaid bills.
- Hold back enough to cover it, and release the rest when conditions are met.
A worked example
Example (illustrative arithmetic, not a standard)
A $60,000 holdback paid in four draws of $15,000. At the final request the work looks 95% done. The inspector lists $3,500 of unfinished punch-list items. A subcontractor has not been paid and could file a $4,000 lien. So the exposure is $3,500 + $4,000 = $7,500. Held funds sit undrawn for 45 days, and the loan rate is 11%. Every figure is a made-up round number.
| Policy | Held back | Exposure not covered | Interest not earned (45 days) |
|---|---|---|---|
| A: release the final draw on photos | $0 | $7,500 | $0 |
| B: 10% retainage on all draws ($6,000) until completion | $6,000 | $1,500 | $81 |
| C: retainage plus 150% of the punch list ($6,000 + $5,250) | $11,250 | $0 | $153 |
Policy B covers $6,000 of the $7,500, leaving $1,500 exposed. Policy C holds enough to cover the whole exposure with $3,750 to spare. The cost of C over A is $153 of interest not earned on funds you have not advanced, which is small next to $7,500 (draw review checklist).
The price is borrower friction: a contractor who wants the last payment and a borrower who wants a sale. That is why the rules must be in the documents from the start and applied the same way on every loan, with the release conditions stated plainly (closing out a loan).
Making it routine
- Put retainage and final-release conditions in every draw agreement, checked by an attorney.
- Require a final inspection report and lien waivers before the last release.
- Release the holdback in writing when the conditions are met, and keep the record.
- Review how much was held back and why at the end of each loan (draw inspections).
Run your own numbers
Use the free fix-and-flip loan sizer below to see the holdback and draw sizes on a loan before you plan its final release.