Lender Site Visit Report: What to Record Before a Draw
A draw request says the work is 60% done. The site says otherwise. A short report, with photos, is how the lender finds out before the money is gone.
What goes in the report
- Header: property, loan, draw number, date, who visited, who met them.
- Photos of each room and system, with the same views each visit.
- Percent complete by scope item, using the approved budget weights (rehab budget review).
- Observations: quality, safety, security, weather damage, insurance concerns (insurance claims).
- Amount supported for release this draw, and why anything is held back (draw schedule).
- A copy of the contractor’s lien waivers for the work paid (lien waivers).
A worked example
Example (illustrative arithmetic, not a recommended method)
A rehab holdback of $47,000. Draw 1 released 30% ($14,100). For draw 2 the contractor reports 60% complete cumulatively, so the request is 60% − 30% = 30% of the holdback. Every figure is a made-up round number.
| Scope item | Budget weight | Contractor’s estimate | Site visit estimate |
|---|---|---|---|
| Demolition and framing | 15% | 100% | 100% |
| Plumbing and electrical rough | 20% | 100% | 90% |
| Drywall and paint | 20% | 65% | 15% |
| Kitchen and baths | 30% | 40% | 30% |
| Flooring and finish | 15% | 0% | 0% |
| Weighted percent complete | 60% | 45% |
Weighted visit estimate: 15 + 18 + 3 + 9 + 0 = 45%. The contractor’s weighted estimate: 15 + 20 + 13 + 12 + 0 = 60%.
| Item | Cumulative | This draw |
|---|---|---|
| Requested (60% of $47,000) | $28,200 | $14,100 |
| Supported by the visit (45% of $47,000) | $21,150 | $7,050 |
| Held back | $7,050 |
The lender releases $7,050, holds back $7,050 and tells the borrower why, in writing, with the photos. The held amount is released when the drywall and finish work catches up. If the lender had paid the full request, $7,050 would have been paid for work not yet done.
Making it routine
- Use the same template on every visit and store it in the loan file (loan file checklist).
- Photograph the same angles each time, so progress is visible.
- Track draws against the schedule on the watch list (watch list).
- Have a lawyer review who does inspections and how the lender describes its role.
Run your own numbers
Use the free fix-and-flip loan sizer below to size the loan and holdback before you plan the draws.