Fixed-Price vs Cost-Plus: Who Carries the Overrun?

By DeskTech HQ · · 2 min read

One contractor offers $55,000 for the whole scope. Another offers to do the same work at cost plus 15%, with an estimate of $48,000 in costs. Both look like about $55,000. They are not the same bet.

The steps

  1. Write the scope in detail so both contracts price the same work (scope of work).
  2. Get the fixed price and the cost-plus estimate and fee in writing (comparing bids).
  3. List a few cost outcomes with rough odds, from savings to a large overrun.
  4. Compute what each contract would cost in each outcome.
  5. Compare the expected cost and the range, and decide how much variation you can carry.

A worked example

Example (illustrative arithmetic, not quotes)

Fixed price: $55,000, plus an assumed $2,500 of change orders on average. Cost-plus: estimated costs of $48,000 and a 15% fee on actual costs. Four made-up outcomes for the contractor’s actual costs: 10% under (20% chance), on estimate (40%), 10% over (25%), 25% over (15%). Every figure is a made-up round number.

Costs vs estimate Odds Fixed price (before extras) Cost-plus ($48,000 × change × 1.15)
10% under 20% $55,000 $49,680
On estimate 40% $55,000 $55,200
10% over 25% $55,000 $60,720
25% over 15% $55,000 $69,000
Expected $57,500 (with $2,500 of extras) $57,546

On average the two cost about the same: $57,500 against $57,546. The range is not the same. The fixed price stays between $55,000 and perhaps $57,500. The cost-plus contract can run from $49,680 to $69,000 (rehab cost overruns).

So the choice is about risk, not price. With a fixed price, the contractor tends to pad the bid for risk and to resist extras. With cost-plus you keep the savings and carry the overruns, and the contractor has less reason to hold costs down unless there is a cap or a share of savings (contingency sizing).

A clear scope favors fixed price. An unclear scope, such as opening walls in an old house, can favor cost-plus with a cap.

Making it routine

  1. Use fixed price when the scope is clear and cost-plus with a cap when it is not.
  2. Define what counts as a cost and how extras are priced, in writing.
  3. Pay against progress, not against the calendar (payment schedules).
  4. Record the final cost against each contract type to learn which suits you.

Run your own numbers

Use the free holding cost calculator below to add the cost of time to either contract.

Quick answers

What is a fixed-price contract?

The contractor agrees to do a defined scope for a set price. If their costs rise, they usually carry the overrun, but changes to the scope are priced as extras.

What is a cost-plus contract?

You pay the contractor's actual costs plus a fee, often a percentage or a set amount. You carry the cost risk, and you also keep any savings.

Which is cheaper?

On average they can be close. The difference is how much the final cost can vary, and who bears it.

What protects me under a cost-plus contract?

A cap or a guaranteed maximum, receipts for every cost, the right to audit, and a clear definition of what counts as a cost. Ask an attorney to review the wording.

Do the numbers in this guide apply to my project?

No. The prices, fees, overrun odds and change orders are made up for the example. They are not quotes or advice about any contract.

Keep reading

Flip project management

Rehab Contingency: Sizing the Buffer by Risk

Learn how to size a rehab contingency by the risk of each line item instead of one flat percentage, with a worked example and its effect on planned profit.

· 1 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.