Fixed-Price vs Cost-Plus: Who Carries the Overrun?
One contractor offers $55,000 for the whole scope. Another offers to do the same work at cost plus 15%, with an estimate of $48,000 in costs. Both look like about $55,000. They are not the same bet.
The steps
- Write the scope in detail so both contracts price the same work (scope of work).
- Get the fixed price and the cost-plus estimate and fee in writing (comparing bids).
- List a few cost outcomes with rough odds, from savings to a large overrun.
- Compute what each contract would cost in each outcome.
- Compare the expected cost and the range, and decide how much variation you can carry.
A worked example
Example (illustrative arithmetic, not quotes)
Fixed price: $55,000, plus an assumed $2,500 of change orders on average. Cost-plus: estimated costs of $48,000 and a 15% fee on actual costs. Four made-up outcomes for the contractor’s actual costs: 10% under (20% chance), on estimate (40%), 10% over (25%), 25% over (15%). Every figure is a made-up round number.
| Costs vs estimate | Odds | Fixed price (before extras) | Cost-plus ($48,000 × change × 1.15) |
|---|---|---|---|
| 10% under | 20% | $55,000 | $49,680 |
| On estimate | 40% | $55,000 | $55,200 |
| 10% over | 25% | $55,000 | $60,720 |
| 25% over | 15% | $55,000 | $69,000 |
| Expected | $57,500 (with $2,500 of extras) | $57,546 |
On average the two cost about the same: $57,500 against $57,546. The range is not the same. The fixed price stays between $55,000 and perhaps $57,500. The cost-plus contract can run from $49,680 to $69,000 (rehab cost overruns).
So the choice is about risk, not price. With a fixed price, the contractor tends to pad the bid for risk and to resist extras. With cost-plus you keep the savings and carry the overruns, and the contractor has less reason to hold costs down unless there is a cap or a share of savings (contingency sizing).
A clear scope favors fixed price. An unclear scope, such as opening walls in an old house, can favor cost-plus with a cap.
Making it routine
- Use fixed price when the scope is clear and cost-plus with a cap when it is not.
- Define what counts as a cost and how extras are priced, in writing.
- Pay against progress, not against the calendar (payment schedules).
- Record the final cost against each contract type to learn which suits you.