Running Two Flips at Once: Profit per Month, Not per Flip
One flip earns $30,000 in six months. Two flips at once should earn twice that in the same six months, and they would, if nothing slowed down. Something usually does, and the question is how much it costs.
The steps
- Write down one flip’s profit and the months it takes alone.
- Estimate the extra months each takes when run together (weekly scorecard).
- Subtract the extra holding cost from each flip’s profit (holding costs).
- Divide the total profit by the total months for each plan.
- Find the delay at which the two plans earn the same per month.
A worked example
Example (illustrative arithmetic, not a forecast)
Each flip earns $30,000 and takes 6 months alone. Holding cost is $1,300 a month per flip, so every extra month removes $1,300 from that flip. Sequential means one flip after the other, 12 months for two. Every figure is a made-up round number.
| Plan | Delay per flip | Profit per flip | Total profit | Months | Profit per month |
|---|---|---|---|---|---|
| Sequential | 0 | $30,000 | $60,000 | 12 | $5,000 |
| Parallel, 2 months slower | 2 | $27,400 | $54,800 | 8 | $6,850 |
| Parallel, 4 months slower | 4 | $24,800 | $49,600 | 10 | $4,960 |
If the overlap costs two months each, running together earns $6,850 a month, 37% more than $5,000. If it costs four months, it earns $4,960 and loses. The break-even is where $60,000 − $2,600 × d equals $5,000 × (6 + d), so $30,000 = $7,600 × d and d is about 3.9 months of delay per flip (profit per hour).
Money is the other limit. Two flips need about twice the peak cash, so the plan only works if both can be funded with a reserve left over (cash cycle).
The practical rule: run two when you have a way to keep each project moving, such as a reliable project manager or contractor, and a record that shows your delays stay small (choosing between deals).
Making it routine
- Record each flip’s planned and actual months, and note when another project was running.
- Use your own overlap delays to decide whether to run a second project.
- Check cash, insurance and lender limits before the second purchase.
- Review profit per month each quarter, not only profit per flip.