The In-Balance Test: Is There Enough Left to Finish?
The borrower asks for the third draw. The site looks fine. The holdback still has money. Whether the money left is enough to finish the house is a different question, and the answer is only visible if someone asks it.
The steps
- Holdback left = original holdback − draws paid.
- Cost to complete = estimate of the remaining work, from the contractor and the site visit (site visit report).
- Balance = holdback left − cost to complete.
- If the balance is zero or more, the loan is in balance. If it is negative, require the shortfall before releasing more.
- Repeat at every draw.
A worked example
Example (illustrative arithmetic, not recommended figures)
A rehab holdback of $47,000. After two draws, $21,150 has been paid (45% of the holdback). The inspector and the contractor agree the work is about 45% complete. The contractor’s estimate to finish is $30,000. Every figure is a made-up round number (draw schedule).
| Step | Calculation | Amount |
|---|---|---|
| Original holdback | $47,000 | |
| Draws paid | $21,150 | |
| Holdback left | $47,000 − $21,150 | $25,850 |
| Cost to complete | contractor estimate, checked on site | $30,000 |
| Balance | $25,850 − $30,000 | −$4,150 |
The loan is out of balance by $4,150. The remaining holdback covers 86.2% of the cost to finish. A balance at different estimates:
| Cost to complete | Balance | Status |
|---|---|---|
| $20,000 | +$5,850 | In balance |
| $25,850 | $0 | Exactly in balance |
| $30,000 | −$4,150 | Out of balance |
| $36,000 | −$10,150 | Out of balance, serious |
The lender asks the borrower to deposit $4,150 into the holdback before releasing the next draw, and records the cost-to-complete estimate and the deposit in the loan file. Releasing the draw anyway would leave the project $4,150 short with no money left to fix it, which is the situation where borrowers stall and liens appear (lien waivers).
Making it routine
- Put the in-balance test and the deposit rule in the loan documents (loan file checklist).
- Do the test with every draw package (draw checklist).
- Put out-of-balance loans on the watch list (watch list).
- Check the contractor’s pricing before you accept the estimate (vetting the contractor).
Run your own numbers
Use the free fix-and-flip loan sizer below to size the loan and holdback together before the first draw.