The In-Balance Test: Is There Enough Left to Finish?

By DeskTech HQ · · 2 min read

The borrower asks for the third draw. The site looks fine. The holdback still has money. Whether the money left is enough to finish the house is a different question, and the answer is only visible if someone asks it.

The steps

  1. Holdback left = original holdback − draws paid.
  2. Cost to complete = estimate of the remaining work, from the contractor and the site visit (site visit report).
  3. Balance = holdback left − cost to complete.
  4. If the balance is zero or more, the loan is in balance. If it is negative, require the shortfall before releasing more.
  5. Repeat at every draw.

A worked example

A rehab holdback of $47,000. After two draws, $21,150 has been paid (45% of the holdback). The inspector and the contractor agree the work is about 45% complete. The contractor’s estimate to finish is $30,000. Every figure is a made-up round number (draw schedule).

Step Calculation Amount
Original holdback $47,000
Draws paid $21,150
Holdback left $47,000 − $21,150 $25,850
Cost to complete contractor estimate, checked on site $30,000
Balance $25,850 − $30,000 −$4,150

The loan is out of balance by $4,150. The remaining holdback covers 86.2% of the cost to finish. A balance at different estimates:

Cost to complete Balance Status
$20,000 +$5,850 In balance
$25,850 $0 Exactly in balance
$30,000 −$4,150 Out of balance
$36,000 −$10,150 Out of balance, serious

The lender asks the borrower to deposit $4,150 into the holdback before releasing the next draw, and records the cost-to-complete estimate and the deposit in the loan file. Releasing the draw anyway would leave the project $4,150 short with no money left to fix it, which is the situation where borrowers stall and liens appear (lien waivers).

Making it routine

  1. Put the in-balance test and the deposit rule in the loan documents (loan file checklist).
  2. Do the test with every draw package (draw checklist).
  3. Put out-of-balance loans on the watch list (watch list).
  4. Check the contractor’s pricing before you accept the estimate (vetting the contractor).

Run your own numbers

Use the free fix-and-flip loan sizer below to size the loan and holdback together before the first draw.

Quick answers

What is an in-balance test?

It compares the money left in the rehab holdback with the estimated cost to finish the work. If the holdback is enough, the loan is in balance. If not, the project is short.

Why test it before every draw?

A project can be 45% complete and 60% paid, or the remaining work can cost more than the budget showed. Testing at each draw catches a shortfall while the borrower can still fix it.

How is the cost to complete estimated?

From the contractor's remaining scope and prices, checked against the site visit and the original budget. It is an estimate, so keep a cushion and update it each time.

What happens when the loan is out of balance?

Many lenders require the borrower to add the shortfall to the holdback or an escrow before more draws are released. The loan documents should say so, and a lawyer should review the wording.

Do the numbers in this guide apply to my loans?

No. The holdback, draws and estimates are made up for the example. They are not recommended figures or a prediction of any project.

Keep reading

Private and hard money lending

A Standard Loan Package: The Loan Count Where It Pays

Learn how to compare the one-time cost of a standard loan document package with the per-loan cost of custom documents, and the loan count where it pays.

· 2 min read

This guide is general education, not legal, tax, or financial advice. Talk with a licensed professional about your situation.